Task Start / End Date

Any critical bugs will be fixed within 24-48 hours.
Also qdPM is in active development so any other issues will be fixed in next versions

Task Start / End Date

Postby elvin.deras » Wed Mar 21, 2012 2:40 pm

We are having problems with Start / End Date for the task, when we add o modify the task we change the start and End Date but in the List of task the Start and End Date appear one day before, please see the following image.

qdpm_task_dates.jpg
qdpm_task_dates.jpg (33.52 KiB) Viewed 950 times
elvin.deras
 
Posts: 10
Joined: Mon Mar 19, 2012 2:40 pm

Re: Task Start / End Date

Postby kindrosker » Wed Mar 21, 2012 5:35 pm

yes I know about this problem
I will be fixed in 8.0 version in this Summer

The issue is with time zone, to display date in listing I'm using javascript data function and it looks like automatically added time zone to date.

I can't send path to fix it because it need to redevelop all items listing
so it will be done in version 8.0

also try to change timezone in configuration to other value, might this is help
User avatar
kindrosker
Site Admin
 
Posts: 132
Joined: Fri Oct 07, 2011 9:42 am

Re: Task Start / End Date

Postby elvin.deras » Wed Mar 28, 2012 4:26 am

Dear,

Should explain me more about how can i configure the time zone as a workaround to fix the dates in the view.

Look now we are using GMT-6 (Tegucigalpa Honduras), in the server and in the client computers, so let me know which time i need to use to see in the correct way the dates.

Thank you in advance.
elvin.deras
 
Posts: 10
Joined: Mon Mar 19, 2012 2:40 pm

Re: Task Start / End Date

Postby kindrosker » Wed Mar 28, 2012 6:55 am

qdPM have own timzone configuration
you can find it in menu Configuration->qdPM->General
see option Timezone
set it to Tegucigalpa Honduras it should help I think
User avatar
kindrosker
Site Admin
 
Posts: 132
Joined: Fri Oct 07, 2011 9:42 am

Re: Task Start / End Date

Postby elvin.deras » Wed Apr 04, 2012 8:42 pm

hmm, i have already the time zone, but the dates doesn't appear correctly.

The server, client and the qdPM have the same time zone (GMT-6) Tegucigalpa Honduras, but the dates appear incorrectly.

Let me know if i need to do a trick as workaround to fix this problem.

Thank you in advance.
elvin.deras
 
Posts: 10
Joined: Mon Mar 19, 2012 2:40 pm

Re: Task Start / End Date

Postby zeluisc » Fri Jun 01, 2012 4:04 pm

Hi

I have same issue, how can resolve this for time zone GMT-londo/lisbon

Advance thanks
JC
zeluisc
 
Posts: 1
Joined: Fri Jun 01, 2012 3:56 pm

Re: Task Start / End Date

Postby kindrosker » Fri Jun 01, 2012 4:18 pm

this issue will be fixed in version 8.0 at the end of this summer
User avatar
kindrosker
Site Admin
 
Posts: 132
Joined: Fri Oct 07, 2011 9:42 am


Return to Bug Report

Who is online

Users browsing this forum: No registered users and 0 guests

cron